How long does it take for building permits?
- Pure Property Insights
- 3 hours ago
- 1 min read
Data gathered by the National Multifamily Housing Council suggests building permit timelines vary widely among municipalities throughout the nation. A March 2026 survey shows the majority said it takes 5-6 months to get them from their local entities.
Survey results show it takes:
Up to 2 months: 2%
3-4 months: 29%
5-6 months: 33%
7-8 months: 10%
9+ months: 14%
The NMHC conducts quarterly surveys to collect this information. See more here.
A majority 55% said jurisdictions are imposing additional project requirements unrelated to the actual project construction.